Sample Questions

Q) The register of interested parties has an output of:

a)Identify Stakeholders.

b) Plan stakeholder management.

c) Control Stakeholder Engagement.

d) Managing Stakeholder Engagement.

Q) An output of the process Develop Project Team:

a) change requests

b) evaluation of the team performance

c) assignments of project personnel

d) update project documents

Q) Manage the continuous production of goods and services to ensure the business continues effectively describes what kind of management?

a) Wallet

b) Project

https://www.coursejoiner.com/wp-admin/options-general.php?page=ad-inserter.php#tab-7

c) Program

d) operations

Q) What kind of manager is assigned the organization running to lead the team that is responsible for achieving the objectives of the project?

a) Program

b) Functional

c) Project

d) Wallet

Q) The sources approaches, tools and data that will be used to perform risk management on a project are determined by:

a) Methodology

b) risk category

c) risk attitude

d) Taking analysis

Who this course is for:

  • Those who want to get knowledge on Certification & Check your Skill Test while attend this Practice Test

Show less

Note : Udemy Courses Coupon will be Expired in 48 Hours. So Enroll Now As Soon As Possible.


0 Comments

Leave a Reply

Your email address will not be published. Required fields are marked *